Energyglobal iconEnergyglobalSep 3, 2026 ~2 min source read

Bungaban Solar advances through approvals, land deals and grid planning

The Bungaban Solar project, developed by a 50:50 joint venture between Windlab and Squadron Energy, has moved through planning approvals, environmental referral and early grid and supply-chain steps as it advances in Queensland.

Bungaban Solar continues to progress through key development milestones

Share this story

Send the public story page.

Useful takeaways from this story.

A referral under Australia’s EPBC Act has been lodged to progress environmental approvals.

Land agreements are in place and a grid connection enquiry with Powerlink has been completed to clarify connection needs.

Market engagement with suppliers and contractors is underway to map out the local and regional supply chain.

# What happened Bungaban Solar, being developed as part of the Bungaban Renewable Energy Hub, has progressed through several practical development steps. The project is a 50:50 joint venture between Windlab and Squadron Energy. Key milestones reported include local planning approval, an environmental referral, land agreements, a grid connection enquiry and supplier engagement.

# Milestones reached June 2025. That approval removes a significant local planning obstacle and allows the project team to advance detailed technical and commercial work.

Following the council approval, the joint venture submitted a referral under the Environment Protection and Biodiversity Conservation (EPBC) Act. The EPBC referral is the formal step toward national environmental assessment and is required before major projects can obtain federal environmental clearances.

The project team has also secured key land agreements with landholders. Those agreements are necessary to progress design, access, site surveys and to lock in footprint and easements ahead of construction planning.

A grid connection enquiry with Powerlink has been completed. That enquiry helps the team understand connection options, constraints and likely technical or network requirements for connecting large-scale solar (and associated infrastructure) to the Queensland transmission grid.

# Commercial and supply-chain activity Market engagement with potential suppliers and contractors has begun. The engagement aims to identify local and regional capability, procurement opportunities and likely delivery pathways for equipment and services as the project moves toward procurement and construction phases.

# Stakeholder engagement The project team intends to continue engaging with landholders, local communities, Traditional Owners, councils, suppliers and other stakeholders as development advances. These ongoing consultations are presented as part of the project's process for securing permissions and confirming impacts and benefits at the community level.

# Project context Bungaban Renewable Energy Hub is presented as part of a broader effort to secure large-scale wind and solar capacity to support Australia's energy transition. The project remains at the development stage, working through approvals, technical studies, commercial arrangements and supply-chain planning before reaching construction-ready status.

# What to watch next

  • Progress and outcomes of the EPBC Act referral and any federal conditions required for approval.
  • Results of detailed grid connection assessments and any network upgrades identified by Powerlink.
  • Procurement milestones, such as selection of EPC contractors or module and inverter suppliers following market engagement.
  • Continued execution of land agreements and the status of stakeholder consultations, including engagement with Traditional Owners and local councils.

# Bottom line

More context around this story.

Hombre Muerto West Project Update
Newswire iconNewswireSep 24, 2026

Hombre Muerto West Project Update

Highlights First LiCl concentrate sales on track: Galan remains on schedule to deliver first lithium chloride (LiCl) concentrate sales from HMW Phase 1 in Q4 CY2026. Impurity separation performing in line with expectations: The nanofiltration plant continues to deliver impurity separation in line with piloting results

Loading more related stories...

Keep reading in the app

Open the app view to save this story, compare related coverage, and continue from the same source.

Open in app