Indiatimes iconIndiatimesSep 24, 2026 ~3 min source read

Allahabad High Court: Accepting delayed possession does not stop buyer claiming interest

In a dispute over a Noida flat, the Lucknow bench of the Allahabad High Court confirmed a buyer’s right to interest for delayed possession despite later accepting the flat. The court rejected the developer’s NGT-based defence and upheld an appellate RERA order requiring interest at one percent above MCLR for the delay period.

Accepting delayed flat possession does not bar homebuyer from claiming interest: Allahabad HC

Share this story

Send the public story page.

Useful takeaways from this story.

A homebuyer who accepts delayed possession can still claim statutory interest for the period of delay.

A developer cannot use an NGT restraint that postdates contractual delay to erase earlier default.

# Case summary Court, Lucknow bench, dismissed an appeal by Antriksh Developers and Promoters Pvt Ltd and reiterated that accepting possession of a flat after delay does not extinguish a buyer's statutory right to interest for the delayed period.

# Parties and project

Developer: Antriksh Developers and Promoters Pvt Ltd. Project: Antriksh Golf View, Sector 78, Noida. Bench: Justice Prashant Kumar (Lucknow bench of Allahabad High Court).

# Timeline of key events

  • NGT restraint: An NGT order restricting construction near Okhla Bird Sanctuary came into effect in August 2013.
  • Developer's completion claim: The developer's case said the project was completed in 2014 and an occupancy-certificate application was filed that year.
  • Offer of possession: Developer offered possession in May 2017, reportedly without an occupancy certificate and other required documents.

# Court's findings The court made several concrete findings:

  • Acceptance of possession later by the buyer does not bar a claim for interest relating to the earlier delay.
  • RERA contains no specific limitation period for claiming interest on account of delayed possession.
  • The developer's argument that an NGT restraint prevented completion was inconsistent with its own claim that the project was completed in 2014 and an occupancy-certificate application was made that year.
  • Court's doctrine of a "zero period" applies only to the actual period affected by an external restraint and cannot wipe out delay already incurred.

# Outcome Tribunal's direction to pay interest for the delayed period and dismissed the developer's appeal.

# Practical implications

  • Claims that a project is both complete and simultaneously prevented by an external order undermine credibility before courts and tribunals.

# What the ruling does not do The court focused on the facts of this dispute and did not create a fixed national rule for interest rates or precise calculation methods beyond upholding the tribunal's direction in this case.

# Short takeaway If a buyer accepts delayed possession, they still can claim interest for the period of delay. Developers should ensure timelines, approvals, and communications are consistent and cannot rely on later-imposed restraints to cancel earlier defaults.

More context around this story.

बिल्डर की देरी पर होम बायर को राहत, पजेशन के बाद भी मिलेगा ब्याज, हाई कोर्ट का आदेश
Tv9hindi iconTv9hindiSep 27, 2026

बिल्डर की देरी पर होम बायर को राहत, पजेशन के बाद भी मिलेगा ब्याज, हाई कोर्ट का आदेश

होम बायर्स के लिए एक अहम फैसले में, इलाहाबाद हाई कोर्ट की लखनऊ बेंच ने स्पष्ट किया है कि फ्लैट का कब्जा लेने के बाद भी देरी के लिए ब्याज मांगने का अधिकार खत्म नहीं होता.

Loading more related stories...

Keep reading in the app

Open the app view to save this story, compare related coverage, and continue from the same source.

Open in app