Los Angeles International Airport's automated People Mover — now called SkyLink — has been delayed again. The system's expected start of passenger service is January 2027, nearly four years after it was initially scheduled to begin operation in 2023. The project began construction in 2019 and is about 99 percent complete. Trains are already running on the elevated guideway without passengers.
What remains before passengers can ride
SkyLink still needs several procedural and technical steps before carrying travelers:
- Complete 30 consecutive days of successful testing.
- Pass an independent review and receive LAWA's assessment.
- Finalize a utility agreement with the Los Angeles Department of Water and Power.
LINXS, the contractor, filed a lawsuit against the city in July over the delays and has said it cannot guarantee the January 2027 date will hold. LAWA emphasizes that safety and reliability are the agency's top priorities and that it will not rush testing or weaken protocols.
The People Mover was designed to link terminals with parking, rental car centers and the Metro Transit Center to reduce car dependence and ease congestion around the airport. For travelers and the city, the system represents a relatively small but practical piece of a larger effort to improve connectivity. Delays have extended public frustration because the physical system looks finished while operational readiness and approvals remain outstanding.
Tension between LAWA and LINXS has been public. LINXS sued the city over responsibility for project delays. A Los Angeles County civil grand jury examined the program and concluded that LINXS was largely responsible for issues that contributed to those delays. Despite that finding, the dispute between the contractor and the airport authority has not produced a firm, unassailable opening date.
LAWA's position is that thorough testing of tracks, signaling and vehicles is standard and necessary for automated airport transit systems. The agency says it will not compromise on safety or reliability even to meet a target date. That position aligns with the need for a driverless train to demonstrate consistent, safe operations before carrying passengers.
- Whether LINXS meets the December completion milestone it projected in filings.
- Finalization of the LADWP utility agreement.
Until those items are cleared, LAWA's projected January 2027 start date should be treated as conditional rather than firm.