Theguardian iconTheguardianSep 27, 2026 ~6 min source read

Datacenter developers accused of using permit tactics to avoid stricter US air-pollution reviews

Environmental advocates say some datacenter projects are broken into multiple 'minor' sources or staggered over time to bypass 'major' source reviews under the Clean Air Act, reducing scrutiny, slowing enforcement and masking cumulative pollution exposures for nearby communities.

Datacenter developers accused of skirting key US pollution rules

Share this story

Send the public story page.

Useful takeaways from this story.

Advocates allege developers split emissions into multiple 'minor' permits or stagger filings so projects avoid 'major' source reviews that require stricter controls and public scrutiny.

Documented examples include Project Jupiter in New Mexico, a North Carolina hyperscale project with 649 diesel backup generators, and clustered datacenters in Frederick, Maryland.

Developers are said to use at least two techniques to avoid major reviews:

  • Divide a single project's emissions into separate, smaller "minor" sources so each stays below federal major-source thresholds.
  • Stagger permit applications over time so individual filings look minor even though the combined project emits as much as a major source.

Those approaches speed approvals, reduce public scrutiny and can lower compliance costs for companies, advocates say.

  • Project Jupiter (New Mexico): Developers proposed two natural gas "microgrids," each in a separate minor permit, even though the combined emissions would have exceeded the major-source threshold for hazardous air pollutants. Regulatory filings show each grid was listed between 20.2 and 24.2 tons per year of hazardous air pollution, while together they could total as much as 44 tons. The application was withdrawn after community and state pushback.
  • North Carolina hyperscale site: Amazon and Duke Energy submitted two permits for backup power at a new center that will use 649 diesel generators. Because the permits were split, the project avoided a major review despite being sited in a low-income area with high existing air pollution.
  • New Jersey enforcement action: A New Jersey datacenter was fined $1.1m after an investigation found dozens of unpermitted generators in operation.

Retired EPA deputy Michael Koerber described the tactic as an attempt to "fly under the radar," calling it "lego permitting." He and other former EPA colleagues point out the permitting shortcuts are not unique to datacenters but have become more noticeable as the industry grows. Attorneys and community groups have characterized some filings — specifically the approach in New Mexico — as an audacious attempt to subdivide what regulators and residents see as a single source.

A major-source review can be lengthy. It can include air-quality modeling that sums the new source with existing regional pollution, pre-construction monitoring, public comment processes and potential requirements to add pollution controls such as scrubbers. By keeping projects officially under minor thresholds, developers can avoid these steps.

Implications for communities and regulators

More context around this story.

Report: former EPA officials identify 30 federal actions since January 2025 that they say exacerbate health risks stemming from data center pollution (Justine Calma/The Verge)
Techmeme iconTechmemeSep 14, 2026

Report: former EPA officials identify 30 federal actions since January 2025 that they say exacerbate health risks stemming from data center pollution (Justine Calma/The Verge)

Justine Calma / The Verge : Report: former EPA officials identify 30 federal actions since January 2025 that they say exacerbate health risks stemming from data center pollution  — The Trump administration is sacrificing Americans' health to build data centers, former EPA officials warn.

Data Centers: US vs. the World [Infographic]
Best Infographics iconBest InfographicsSep 22, 2026

Data Centers: US vs. the World [Infographic]

Data centers have become quite a hot topic these days. There is a lot of talk about who should control AI and at what pace development should happen. Have you ever wondered how the US stacks up against the world when it comes to data centers? This infographic takes a look: The post Data Centers: US vs. the World [Infog