Broken Hill Gold pours third doré bar as White Dam moves toward restart

ASX-listed Broken Hill Gold produced a third doré bar from the White Dam copper–gold project and has completed processing-tank and gold-room upgrades as it prepares to restart operations.

Share this story

Send the public story page.

Useful takeaways from this story.

Broken Hill Gold poured a third doré bar weighing 5.43 kg (174 oz) and shipped it to the Perth Mint for assay and processing.

The company built a new carbon-in-column tank to replace an existing unit in the White Dam processing circuit.

Upgrades to the gold room facility have been completed to support resumed processing activities ahead of the White Dam restart.

The useful part

ADVANCED SEARCH Clear Search SEARCH Sponsored by Saving articles Articles can be saved for quick future reference. Registered viewers will receive email access to each episode as it is released. When you select a default region you will be directed to the MiningWeekly.com home page of your choice whenever you visit miningweekly.com.

How it works

  • If you have previously accessed your free report, you can purchase additional Research Reports by clicking on the "Buy Report" button on this page.
  • The most cost-effective way to access all our Research Reports is by subscribing to Creamer Media's Research Channel Africa.
  • At the time of your subscription, Creamer Media's subscriptions department will be in contact with you to ensure that you receive a copy of your preferred Research Report.
  • Drilling is underway to collect samples for column leach testwork on Vertigo East and Vertigo North, with initial pit design work now forecast to be completed during October.
  • Reuters URANIUM Skeleton Coast Uranium completes digitisation of historical Namibia exploration data 2nd October 2026 By:

What to take from it

VISIT SHOWROOM MORE Latest Multimedia sponsored by Audio Articles Drone upliftment, manganese through Namibia, Sibanye-Stillwater trading on the A2X make headlines 2nd October 2026 MANGANESE LOGISTICS South Africa risks leaving much manganese value unrealised if logistics issues persist 2nd October 2026 By: This setting is controlled by cookies and should your cookies be re-set you will then be directed to the regional edition associated with the geographic location of our IP address. Should your cookies be reset then you may again use the menu to select a default region.

Example or evidence

  • Please indicate if your feedback is in the form of a letter to the editor that you wish to have published.
  • If so, please be aware that we require that you keep your feedback to below 300 words and we will consider its publication online or in Creamer Media's print publications, at Creamer Media's discretion.
  • We also welcome factual corrections and tip-offs and will protect the identity of our sources, please indicate if this is your wish in your feedback below.
  • Your Feedback: 300 characters remaining Letter to the editor Factual correction Tip off Verification:

Details worth keeping

anywhere in the article search headings only in the first paragraph With? all these words any of these words this exact phrase. Email This Article To: separate emails by commas, maximum limit of 4 addresses From:

Related coverage

  • Newswire: Gold & silver Resource upgrades pending, PFS on track for Q1 CY27
  • Newswire: First step completed in Mining Lease (ML) approvals process HIGHLIGHTS Environmental Scoping Report approved by Department for Energy & Mining (DEM) South Australia, establishing the official terms of...
  • Brisbanetimes: Forrestania Resources has bolstered its WA gold inventory, tabling a new 285,700-ounce resource for its Ladies project and lifting high-confidence ounces by 43 per cent.

More context around this story.

Hombre Muerto West Project Update
Newswire iconNewswireSep 24, 2026

Hombre Muerto West Project Update

Highlights First LiCl concentrate sales on track: Galan remains on schedule to deliver first lithium chloride (LiCl) concentrate sales from HMW Phase 1 in Q4 CY2026. Impurity separation performing in line with expectations: The nanofiltration plant continues to deliver impurity separation in line with piloting results

Tunkillia Environmental Scoping Report Approved
Newswire iconNewswireSep 7, 2026

Tunkillia Environmental Scoping Report Approved

First step completed in Mining Lease (ML) approvals process HIGHLIGHTS Environmental Scoping Report approved by Department for Energy & Mining ( DEM ) South Australia, establishing the official terms of reference for Tunkillia's development approvals processes Updated JORC Mineral Resource Estimates ( MRE ) pending for

Loading more related stories...

Keep reading in the app

Open the app view to save this story, compare related coverage, and continue from the same source.

Open in app